  • Project Type:

    Mine Development

  • Project Name:

    Doris North Mine

Applicant
Primary Contact
Regulatory Authorities
External Links

The Doris North Gold Project was assessed by the NIRB from 2002 - 2006. It was approved to proceed on September 15, 2006 subject to the terms and conditions of Project Certificate No. 005. This project dashboard contains the original assessment original assessment information as well as monitoring information through to the approval of an amended Project Certificate associated with the Proposed Modifications to the Doris North Gold Mine Project in 2016.



Modified from the 2005 Project Description: The Doris North Gold Mine Project is a gold mine and associated facilities located approximately 65 kilometres (km) to the east of Omingmaktok (Bay Chimo) and 110 km south of Cambridge Bay, in the Kitikmeot Region as proposed by Miramar Hope Bay Limited. The Project involves an underground gold mine and associated infrastructure with an ore processing capacity of 668 tonnes per day.

The project life of the mine is planned for five (5) years (1 year of construction, 2 years of operations, and 2 years of closure and post-closure activities) involving the processing 458,000 tonnes of ore to yield approximately 306,830 ounces of gold. Construction is proposed to start in 2007.

Project infrastructure includes an underground mine and ramp to access the workings, water management infrastructure; waste rock storage facilities, ore processing plant tailings impoundment facility, power plant, fuel tank farm(s), explosives storage area, airstrip (including a float plan dock), haul and service roads; water treatment plant, incinerator, sewage treatment facility, maintenance facility, and accommodations and camp facilities for up to 175 personnel.

Supplies are shipped to Roberts Bay during the open water season which includes a 103-metres jetty, and a laydown area. Transportation to the mine occurs via a 4.8 km all-weather access road.

Assessment Phase / Activity
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2024-01-17
  • NIRB Notice to Parties re Proponent Response received 2023-09-29
  • Send Notification to Parties 2023-09-20
  • NIRB Issues Site Visit Report 2023-09-14
  • Send Notification to Parties 2023-08-29
  • Send Notification to Parties 2023-08-17
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2023-08-17
  • Send Notification to Parties 2023-06-26
  • Send Notification to Parties 2023-06-16
  • NIRB Ltr to Parties requesting comments on report. 2023-07-04
  • Send Notification to Parties 2023-05-10
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2023-03-24
  • NIRB Issues Site Visit Report 2023-02-13
  • Send Notification to Parties 2022-08-08
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2022-08-08
  • Send Notification to Parties 2022-06-27
  • Send Notification to Parties 2022-05-17
  • NIRB Ltr to Parties requesting comments on report. 2022-05-17
  • Technical advisor assigned 2022-04-06
  • Technical advisor assigned 2022-03-31
  • Send Notification to Parties 2022-01-24
  • Technical advisor assigned 2022-01-20
  • NIRB Final Monitoring Report: Sent to Distribution 2021-11-09
  • NIRB Issues Site Visit Report 2021-10-12
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2021-10-12
  • NIRB Notification to Parties Comments Received 2021-07-08
  • NIRB Ltr to Parties requesting comments on report. 2021-07-08
  • NIRB Ltr to Parties requesting comments on report. 2021-06-04
  • Send Notification to Parties 2021-04-09
  • NIRB Notice to Parties re comments received 2021-03-24
  • Send Notification to Parties 2021-03-11
  • Send Notification to Parties 2021-01-06
  • NIRB Issues Site Visit Report 2020-12-04
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2020-12-03
  • NIRB Issues Site Visit Report 2020-10-22
  • NIRB issues notice of community information sessions 2020-08-12
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2020-08-12
  • NIRB issues notice of community information sessions 2020-07-31
  • NIRB Notification to Parties Comments Received 2020-07-30
  • Technical advisor assigned 2020-07-29
  • NIRB Ltr to Parties requesting comments on report. 2020-07-29
  • Technical advisor assigned 2019-10-28
  • Technical advisor assigned 2019-10-28
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-10-25
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-10-25
  • NIRB Issues Site Visit Report 2019-09-23
  • NIRB Notice to Parties re comments received 2019-08-06
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2019-08-06
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-07-24
  • NIRB Ltr to Parties requesting comments on report. 2019-07-09
  • NIRB Ltr to Parties requesting comments on report. 2019-07-08
  • NIRB Ltr to Parties requesting comments on report. 2019-05-27
  • Technical advisor assigned 2018-11-27
  • Send Notification to Parties 2018-11-22
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-11-22
  • NIRB Notice to Parties re Proponent Response received 2018-07-30
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2018-07-30
  • NIRB Ltr to Parties requesting comments on report. 2018-07-04
  • NIRB Ltr to Parties requesting comments on report. Extended 2018-06-15
  • NIRB Ltr to Parties requesting comments on report. 2018-05-22
  • Send Notification to Parties 2017-12-12
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-19
  • Send Notification to Parties 2017-10-13
  • Technical advisor assigned 2017-10-13
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-10-11
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-10-11
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-08-07
  • NIRB Ltr to Parties requesting comments on report. 2017-07-12
  • NIRB Ltr to Parties requesting comments on report. 2017-07-14
  • NIRB Received Report From Proponent 2017-04-21
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-06
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-04
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-04
  • Request for Reconsideration of Project Certificate Terms and Conditions Received 2017-02-13
  • Received Required Reporting From Proponent 2017-01-31
  • NIRB Final Monitoring Report: Sent to Distribution 2016-11-04
  • NIRB issues notice of community information sessions 2016-10-05
  • NIRB Issues Amended Project Certificate to Proponent 2016-09-23
  • NIRB Issues Amended Project Certificate to Proponent 2016-09-23
  • NIRB Issues Notice to Parties re Guidelines development workshop 2016-09-19
  • NIRB Notice to Parties re comments received 2016-09-14
  • NIRB Notice to Parties re comments received 2016-09-14
  • NIRB Notice to Parties re Project Certificate Workshop 2016-08-31
  • NIRB Notification to Proponents Received 2016-08-30
  • NIRB Received Minister’s decision re Final Hearing Report 2016-08-30
  • Annual Report: Commenting started 2016-08-22
  • NIRB Ltr to Minister(s) re Final Hearing Report 2016-06-13
  • Technical advisor assigned 2016-01-29
  • Started project monitoring 2006-08-26
Region
  • Kitikmeot
Project Images
Document Categories (click to open )
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account