Project Dashboard

Status: ACTIVE MONITORING

  • NIRB File No:

    08MN053

  • Application No.:

    123910

  • Project Type:

    Mine Development

  • Project Name:

    Mary River Project

Applicant
Primary Contact

The Mary River Project was assessed by the NIRB from 2008 – 2012. It was approved to proceed on December 28, 2012 subject to the terms and conditions of Project Certificate No. 005. This project dashboard contains the original assessment information as well as monitoring information through to the approval of an amended Project Certificate associated with the Early Revenue Phase Proposal in 2014.

Modified from the 2008 Project Description: The Mary River Project (“the Project”) is a proposed iron ore mine and associated facilities located on North Baffin Island, in the Qikiqtani Region of Nunavut. The Project involves the construction, operation, closure, and reclamation of an 18 million tonne-per-annum (Mt/a) open pit mine. The high-grade iron ore to be mined is suitable for international shipment after only crushing and screening and as such, no chemical processing facilities are required for this Project. A railway system will transport the ore from the mine area to an all-season deep-water port and ship loading facility at Steensby Inlet where the ore will be loaded into ore carriers for overseas shipment through Foxe Basin. A dedicated fleet of cape-sized ore carriers, capable of breaking ice, will be chartered by Baffinland from a consortium of ship owners organized by Fednav. Some non-icebreaking ore carriers and conventional ships will also be used during the open water season.

All major Project components will operate year round and, based on the currently-defined iron ore reserve, will continue to operate for about 21 years. Geological conditions suggest that additional ore may be delineated as exploration continues, potentially extending the life and/or increasing the production rate of the Project.

The Mary River site is located about 160 km south of the community of Pond Inlet (Mittimatalik) and 1000 km northwest of Iqaluit, the capital of Nunavut. Project facilities will be sited in the mine area at Mary River and port area at Steensby Inlet, with a railway line and access road connecting the two. Marine access and shipping through the construction phase and periodically during operation will occur seasonally through Milne Inlet and the existing Milne Inlet Tote Road will therefore be used periodically to access Mary River during frozen conditions. Shipping through Steensby Inlet will be seasonal through construction and year-round through operation. Access to the Project sites for personnel will be by chartered aircraft.

Assessment Phase / Activity
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-07-08
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-07-08
  • Send Notification to Parties 2020-07-02
  • Send Notification to Parties 2020-07-02
  • Additional Plans: Due Date set 2020-06-30
  • NIRB Issues Amended Project Certificate to Proponent 2020-06-26
  • Additional Plans: Due Date set 2020-06-25
  • NIRB Issues Amended Project Certificate to Proponent 2020-06-19
  • NIRB Issues Amended Project Certificate to Proponent 2020-06-18
  • NIRB Issues Amended Project Certificate to Proponent 2020-06-18
  • NIRB Ltr to Parties requesting comments on report. 2020-06-16
  • NIRB Notice receipt of comments 2020-06-09
  • NIRB Issues Site Visit Report 2020-06-09
  • Additional Plans: Due Date set 2020-06-05
  • Send Notification to Parties 2020-05-27
  • Additional Plans: Due Date set 2020-05-25
  • NIRB Issues Site Visit Report 2020-05-12
  • NIRB Issues Site Visit Report 2020-05-13
  • Send Notification to Parties 2020-04-24
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-04-24
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-04-24
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-04-23
  • Send Notification to Parties 2020-04-21
  • Additional Plans: Due Date set 2020-04-20
  • Additional Plans: Due Date set 2020-04-16
  • Additional Plans: Due Date set 2020-04-16
  • Additional Plans: Due Date set 2020-04-16
  • Additional Plans: Due Date set 2020-04-14
  • Additional Plans: Due Date set 2020-04-14
  • Additional Plans: Due Date set 2020-04-14
  • Send Notification to Parties 2020-04-03
  • Send Notification to Parties 2020-04-03
  • Additional Plans: Due Date set 2020-03-23
  • Send Notification to Parties 2020-03-17
  • Send Notification to Parties 2020-03-13
  • NIRB Notice receipt of comments 2020-03-12
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-03-12
  • Additional Plans: Due Date set 2020-03-05
  • NIRB Ltr to Minister(s) re Final Hearing Report 2020-03-04
  • NIRB Ltr to Minister(s) re Final Hearing Report 2020-03-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-03-04
  • Send Notification to Parties 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-25
  • Additional Plans: Due Date set 2020-02-24
  • NIRB Notice to Parties re comments received 2020-02-14
  • NIRB Notice to Parties re comments received 2020-02-14
  • Send Notification to Parties 2020-02-13
  • Send Notification to Parties 2020-02-11
  • Send Notification to Parties 2020-02-10
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-02-10
  • Additional Plans: Due Date set 2020-02-04
  • NIRB Notice to Parties re receipt of final written submissions 2020-02-03
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-01-29
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-01-28
  • NIRB Notice to Parties re proponent response to final written submissions 2020-01-28
  • Additional Plans: Due Date set 2020-01-28
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • Send Notification to Parties 2020-01-24
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2020-01-24
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2020-01-24
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2020-01-24
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2020-01-24
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2020-01-24
  • Additional Plans: Due Date set 2020-01-21
  • Send Notification to Parties 2020-01-20
  • NIRB Issues Site Visit Report 2020-01-20
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-01-10
  • NIRB Notice to Parties re comments received 2020-01-07
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-01-07
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2020-01-07
  • Send Notification to Parties 2020-01-02
  • Send Notification to Parties 2020-01-02
  • Send Notification to Parties 2019-12-17
  • Send Notification to Parties 2019-12-16
  • Send Notification to Parties 2019-12-16
  • Send Notification to Parties 2019-12-16
  • Send Notification to Parties 2019-12-13
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2019-12-09
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2019-12-09
  • NIRB Issues Site Visit Report 2019-12-02
  • Send Notification to Parties 2019-12-02
  • Send Notification to Parties 2019-12-02
  • NIRB Notice to Parties re Final Hearing Transcripts 2019-11-29
  • Send Notification to Parties 2019-11-26
  • NIRB Notice to Parties re Final Hearing Transcripts 2019-11-26
  • Send Notification to Parties 2019-11-22
  • Send Notification to Parties 2019-11-21
  • Additional Plans: Due Date set 2019-11-19
  • Send Notification to Parties 2019-11-18
  • Send Notification to Parties 2019-11-15
  • Send Notification to Parties 2019-11-15
  • Send Notification to Parties 2019-11-14
  • Send Notification to Parties 2019-11-13
  • Send Notification to Parties 2019-11-13
  • Send Notification to Parties 2019-11-01
  • Send Notification to Parties 2019-11-01
  • Send Notification to Parties 2019-11-01
  • Send Notification to Parties 2019-10-31
  • Send Notification to Parties 2019-10-30
  • Send Notification to Parties 2019-10-29
  • Send Notification to Parties 2019-10-28
  • Send Notification to Parties 2019-10-25
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-10-25
  • NIRB Ltr to Dist re Draft Hearing Agenda 2019-10-25
  • Additional Plans: Due Date set 2019-10-18
  • Additional Plans: Due Date set 2019-10-18
  • Additional Plans: Due Date set 2019-10-17
  • NIRB Notice to Parties re proponent response to final written submissions 2019-10-17
  • Additional Plans: Due Date set 2019-10-15
  • NIRB Ltr to Mayor re Opening Remarks 2019-10-10
  • Additional Plans: Due Date set 2019-10-10
  • Additional Plans: Due Date set 2019-10-10
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-10-10
  • NIRB Notice to Parties re receipt of Proponent response to site visit follow up 2019-10-07
  • Send Notification to Parties 2019-10-04
  • Send Notification to Parties 2019-10-04
  • Send Notification to Parties 2019-10-04
  • NIRB Issues Site Visit Report 2019-10-03
  • Send Notification to Parties 2019-10-02
  • Send Notification to Parties 2019-10-02
  • Additional Plans: Commenting started 2019-10-02
  • NIRB Notice to Parties re receipt of final written submissions 2019-09-30
  • NIRB Notice to Parties re receipt of final written submissions 2019-09-30
  • Send Notification to Parties 2019-09-27
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Send Notification to Parties 2019-09-24
  • Additional Plans: Commenting started 2019-09-23
  • NIRB Notice to Parties re receipt of final written submissions 2019-09-23
  • Additional Plans: Due Date set 2019-09-19
  • Additional Plans: Due Date set 2019-09-18
  • Additional Plans: Due Date set 2019-09-16
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-06
  • Additional Plans: Due Date set 2019-09-04
  • NIRB Issues notification of planned site visit 2019-08-29
  • NIRB Issues Site Visit Report 2019-08-28
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-08-28
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-08-27
  • NIRB Notice to Parties re Public Hearing Date Set 2019-08-22
  • NIRB Notice to Parties re Public Hearing Date Set 2019-08-21
  • NIRB Notice to Parties re Public Hearing Date Set 2019-08-21
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-08-20
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-08-15
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-08-15
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-07-31
  • Additional Plans: Due Date set 2019-07-30
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-07-25
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2019-07-25
  • NIRB Notice to Parties re Public Hearing Date Set 2019-07-25
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-07-25
  • Additional Plans: Due Date set 2019-07-19
  • Additional Plans: Due Date set 2019-07-19
  • Additional Plans: Due Date set 2019-07-19
  • Additional Plans: Due Date set 2019-07-19
  • Additional Plans: Due Date set 2019-07-17
  • Additional Plans: Due Date set 2019-07-16
  • NIRB Notification to Parties Comments Received 2019-07-16
  • NIRB Notification to Parties Comments Received 2019-07-16
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-07-16
  • NIRB received correspondence form Proponent and / or parties re anticipated IR response date 2019-07-15
  • Send Notification to Parties 2019-07-04
  • Send Notification to Parties 2019-06-28
  • NIRB Notification to Parties Comments Received 2019-06-25
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-06-25
  • Send Notification to Parties 2019-06-24
  • Send Notification to Parties 2019-06-24
  • Send Notification to Parties 2019-06-17
  • Send Notification to Parties 2019-06-17
  • Send Notification to Parties 2019-06-17
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-17
  • Send Notification to Parties 2019-06-17
  • Send Notification to Parties 2019-06-17
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-14
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-14
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-07-12
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-14
  • NIRB Notification to Parties Comments Received 2019-06-12
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-12
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-07
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-06-07
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-06-06
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-06-06
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-06-06
  • Additional Plans: Due Date set 2019-06-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-31
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-31
  • NIRB Ltr to Parties re Community Information summary report 2019-05-28
  • Send Notification to Parties 2019-05-27
  • Send Notification to Parties 2019-05-27
  • Additional Plans: Due Date set 2019-05-27
  • Additional Plans: Due Date set 2019-05-27
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-27
  • Technical advisor assigned 2019-05-22
  • Technical advisor assigned 2019-05-22
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-16
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-16
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-05-14
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-05-10
  • Additional Plans: Commenting 2019-05-08
  • NIRB Ltr to Parties re Community Information summary report 2019-05-06
  • Additional Plans: Due Date set 2019-05-01
  • Additional Plans: Due Date set 2019-04-29
  • NIRB Ltr to Parties requesting comments on report. 2019-04-29
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-04-26
  • Technical advisor assigned 2019-04-18
  • Technical advisor assigned 2019-04-18
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-04-18
  • NIRB Notice receipt of comments 2019-04-15
  • NIRB Received Report From Proponent 2019-04-10
  • Additional Plans: Due Date set 2019-04-10
  • NIRB Received Report From Proponent 2019-04-08
  • Send Notification to Parties 2019-04-08
  • Send Notification to Parties 2019-04-05
  • Additional Plans: Due Date set 2019-04-05
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-04-05
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-04-03
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-29
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-27
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-27
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-27
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments Extended 2019-03-27
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-27
  • Send Notification to Parties 2019-03-26
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-26
  • Guidelines: NIRB issues guidelines to proponent 2019-03-19
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-19
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-18
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-14
  • Additional Plans: Commenting 2019-03-13
  • Additional Plans: Commenting in progress 2019-03-11
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-11
  • Additional Plans: Due Date set 2019-03-06
  • NIRB Notice to Parties re receipt of Proponent response to site visit follow up 2019-03-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-04
  • Additional Plans: Commenting 2019-03-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-03-01
  • Additional Plans: Commenting 2019-03-01
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-03-01
  • Additional Plans: Commenting 2019-02-25
  • NIRB Notice to parties re receipt of IR responses 2019-02-12
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-02-12
  • NIRB Notice to Parties re Proponent response received 2019-02-11
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-02-11
  • Send Notification to Parties 2019-02-05
  • Send Notification to Parties 2019-02-05
  • Send Notification to Parties 2019-02-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-02-04
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-01-30
  • NIRB Notice to Parties re acceptance of intervenor status 2019-01-24
  • NIRB Ltr to Proponent and Parties re IRs requiring a response 2019-01-24
  • Send Notification to Parties 2019-01-14
  • Send Notification to Parties 2019-01-02
  • Send Notification to Parties 2019-01-02
  • NIRB Notice to Parties re Proponent Response received 2018-12-24
  • Send Notification to Parties 2018-12-21
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2019-02-21
  • NIRB Notice to parties re receipt of IR responses 2018-12-19
  • NIRB Notice to parties re receipt of IR responses 2018-12-18
  • NIRB Notice to Parties re receipt of final written submissions 2018-12-17
  • NIRB Notice to Parties re Proponent Response received 2018-12-17
  • NIRB Notice to Parties re Proponent Response received 2018-12-17
  • NIRB Notice to Parties re Proponent Response received 2018-12-17
  • NIRB Notice to Parties re Proponent Response received 2018-12-17
  • NIRB Notice to Parties re Proponent Response received 2018-12-17
  • Send Notification to Parties 2018-12-17
  • Send Notification to Parties 2018-12-17
  • Send Notification to Parties 2018-12-17
  • Send Notification to Parties 2018-12-11
  • NIRB received correspondence form Proponent and / or parties re anticipated IR response date 2019-01-09
  • NIRB Ltr to Proponent and Parties re IRs requiring a response 2018-12-31
  • Send Notification to Parties 2018-11-28
  • NIRB Ltr to Proponent and Parties re IRs requiring a response 2018-11-28
  • Send Notification to Parties 2018-11-21
  • Technical advisor assigned 2018-11-21
  • Technical advisor assigned 2018-11-21
  • NIRB Ltr to Parties re submission of Information Requests 2018-11-21
  • Send Notification to Parties 2018-11-14
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-11-14
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-11-08
  • NIRB Issues Amended Project Certificate to Proponent 2018-11-07
  • NIRB Ltr to Parties re submission of Information Requests 2018-11-07
  • NIRB Issues Amended Project Certificate to Proponent 2018-10-30
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2018-11-13
  • NIRB issues notice of receipt of final EIS submission 2018-10-10
  • NIRB Received Minister’s decision re Final Hearing Report 2018-10-02
  • NIRB Received Minister’s decision re Final Hearing Report 2018-10-02
  • NIRB Ltr to Proponent re FEIS Compliance Determination 2018-09-14
  • NIRB Ltr to Minister(s) re Final Hearing Report 2018-08-31
  • NIRB Ltr to Minister(s) re Final Hearing Report 2018-08-31
  • NIRB issues notice of receipt of final EIS submission 2018-08-23
  • Guidelines: NIRB issues guidelines to proponent 2018-08-21
  • NIRB Notice to Parties re proponent response to final written submissions 2018-08-10
  • NIRB issues notice of community information sessions 2018-08-03
  • NIRB issues notice of community information sessions 2018-08-01
  • NIRB Notice to Parties re receipt of final written submissions 2018-07-27
  • NIRB Ltr to Parties re anticipated FEIS submission date 2018-07-26
  • NIRB Ltr to Parties re anticipated FEIS submission date 2018-07-19
  • Send Notification to Parties 2018-07-17
  • NIRB Notice to Parties re comments received 2018-07-12
  • NIRB Notice to Parties re comments received 2018-07-12
  • Send Notification to Parties 2018-07-10
  • NIRB issues notice of community information sessions 2018-06-29
  • NIRB Notice to Parties re receipt of final written submissions 2018-06-27
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-26
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-26
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-11
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-06
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2018-07-12
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2018-05-30
  • NIRB Ltr to Parties requesting comments on report. 2018-05-14
  • NIRB Ltr to Parties requesting comments on report. 2018-04-23
  • NIRB Issues notification of planned site visit 2018-03-16
  • Send Notification to Parties 2017-12-12
  • NIRB Notice to Parties re comments received 2017-11-30
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-19
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-11-27
  • NIRB Ltr to Proponent re Conformity Determination required 2017-11-14
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-11-17
  • NIRB Ltr to Proponent re reconsideration of Project Certificate 2017-10-26
  • NIRB Ltr to Proponent re reconsideration of Project Certificate 2017-10-26
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-29
  • NIRB Ltr to proponent re additional information required 2017-09-22
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-13
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-07
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-06
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-01
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-01
  • Send Notification to Parties 2017-09-01
  • Send Notification to Parties 2017-08-31
  • NIRB Issues Correspondence to Parties re Project Certificate Terms and Conditions 2017-08-22
  • NIRB Ltr to proponent re additional information required 2017-08-21
  • NIRB Issues notification of planned site visit 2017-08-01
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-28
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-04
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-05-30
  • NIRB Ltr to Parties requesting comments on report. 2017-05-31
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-06
  • NIRB issues notice of community information sessions 2017-03-14
  • NIRB issues notice of community information sessions 2017-03-13
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2016-12-21
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-19
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-15
  • NIRB Notice to Parties re Proponent response received 2016-12-15
  • NIRB Notice to Parties re Proponent response received 2016-12-15
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-07
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2016-12-02
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-11-03
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-10-28
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2016-08-04
  • NIRB Notification to Proponents Received 2016-06-30
  • Annual Report: Commenting completed 2016-06-27
  • NIRB Received Report From Proponent 2016-04-22
  • Technical advisor assigned 2016-01-29
  • Started project monitoring 2010-07-15
Region
  • North Baffin
Project Images
Document Categories (click to open )
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account