Project Dashboard
Status: ACTIVE MONITORING
-
NIRB File No:
12MN001
-
Application No.:
124148
-
Project Type:
Mine Development
-
Project Name:
Phase 2 Hope Bay Belt Project
Active Monitoring
- NIRB Monitoring Commences 2018-11-09
- Proponent Annual Report Received 2020-05-01
- NIRB Site Visit 2020-10-22
- NIRB Annual Report Issued 2020-12-03
- Project Certificate Reconsideration 2018-11-09
- Completed Monitoring
Applicant
- Agnico Eagle Mines Ltd.
- Manon Turmel
- 93 Rue Arseneault
- Val d'Or, Quebec J9P0E9 Canada
- manon.turmel@agnicoeagle.com
Primary Contact
- Agnico Eagle Mines Limited
- Agnico Eagle
- 11600 Louis-Bisson
- Mirabel, Quebec J7N 1G9 Canada
- Tel: 819-759-3555
- nunavut.environment.permitting@agnicoeagle.com
Regulatory Authorities
Related Projects
External Links
Project Summary
The Phase 2 Hope Bay Project was assessed by the NIRB from 2012 – 2018. It was approved to proceed on November 9, 2018, subject to the terms and conditions of Project Certificate No. 009. This project dashboard contains the original assessment information as well as monitoring information from 2018 onward.
Modified from the 2016 Project Description: The Phase 2 Hope Bay Project involves the underground and above ground mining of three gold deposits (Madrid North, Madrid South, and Boston) located at the Hope Bay property, approximately 150 kilometres (km) southwest of Cambridge Bay in the Western Kitikmeot, Nunavut, and approximately 700 km northeast of Yellowknife.
The total mineral reserves at the Madrid North, Madrid South, and Boston sites, based on a cut-off grade of 4.5 grams per tonne, is estimated to be approximately 4.8 million ounces of gold. The project is associated with the Doris North Gold Mine Project (05MN047) and uses some of the existing infrastructure at the Doris North Gold Mine site to support development of the three additional deposits. Ore from the North and South Madrid sites and ore concentrate from the Boston site is trucked to the mill at the Doris North site via improvements to the existing all-weather road (already constructed to support advanced exploration) between the Madrid sites and Doris North site, and the construction of a 55 km extension of the existing Doris North-Madrid all weather haul road linking the Boston site to the Doris North-Madrid haul road.
The ore is mined by underground mining methods with portions of the ore near the surface recovered by surface mining methods. As part of the mining activities for the Project, infrastructure at the Doris North and the Roberts Bay sites is expanded in addition to the construction and operation of new infrastructure at the Madrid and Boston sites, including a camp/accommodation facility, airstrip, ore processing and tailings facilities at the Boston site. Fuel tank farms, waste rock storage facilities, ore stockpiling facilities, water management infrastructures, and water treatment facilities are located at both Madrid and Boston sites.
The project workforce is 870, with 400 personnel housed at an expanded camp at the existing Doris North site and 300 personnel housed at the camp at the Boston site. The proposed life of the Project, from mobilization and construction to operation, closure and post-closure, is 19 years. Construction begins in 2019, with a five-year construction phase (Year 1 to Year 5), a 14-year operations phase (Year 1 to Year 14), a six-year closure phase (Year 12 to Year 17), and a six-year post-closure phase (Year 14 to Year 19).
The existing marine infrastructure in Roberts Bay is used to support shipment of materials required for construction of the Project as well as annual resupply of fuel, with all shipping taking place during the open water season. The Project also includes the addition of up to six (6) wind turbines, generators and associated power transmission lines to power the Project, as well as additional fuel storage infrastructure at the mine sites.
Assessment Phase / Activity
- Send Notification to Parties 2024-11-01
- Technical advisor assigned 2024-10-29
- NIRB Issues Site Visit Report 2024-09-11
- NIRB Notice to Parties re Proponent Response received 2024-08-02
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2024-07-05
- Technical advisor assigned 2024-07-02
- Technical advisor assigned 2024-07-02
- Send Notification to Parties 2024-05-22
- NIRB Ltr to Parties requesting comments on report. 2024-05-09
- Technical advisor assigned 2024-05-07
- Technical advisor assigned 2024-05-07
- NIRB Issues Monitoring Report and Recommendations for Proponent 2024-01-17
- NIRB Notice to Parties re Proponent Response received 2023-09-29
- NIRB Issues Site Visit Report 2023-09-14
- Send Notification to Parties 2023-08-29
- Send Notification to Parties 2023-08-17
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2023-08-17
- Send Notification to Parties 2023-06-26
- Send Notification to Parties 2023-06-16
- NIRB Ltr to Parties requesting comments on report. 2023-07-04
- Send Notification to Parties 2023-05-10
- NIRB Issues Monitoring Report and Recommendations for Proponent 2023-03-24
- NIRB Issues Site Visit Report 2023-02-13
- Send Notification to Parties 2022-08-08
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2022-08-08
- Send Notification to Parties 2022-06-27
- Send Notification to Parties 2022-05-17
- NIRB Ltr to Parties requesting comments on report. 2022-05-17
- Technical advisor assigned 2022-04-06
- Technical advisor assigned 2022-03-31
- Send Notification to Parties 2022-01-24
- Technical advisor assigned 2022-01-20
- NIRB Final Monitoring Report: Sent to Distribution 2021-11-09
- NIRB Issues Site Visit Report 2021-10-12
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2021-10-12
- NIRB Ltr to Parties requesting comments on report. 2021-07-14
- NIRB Notice to Parties re comments received 2021-03-24
- NIRB Issues Site Visit Report 2020-12-04
- NIRB Issues Monitoring Report and Recommendations for Proponent 2020-12-04
- NIRB Issues Site Visit Report 2020-10-22
- NIRB issues notice of community information sessions 2020-08-12
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2020-08-12
- NIRB issues notice of community information sessions 2020-07-31
- NIRB Notification to Parties Comments Received 2020-07-30
- NIRB Ltr to Parties requesting comments on report. 2020-07-27
- NIRB Issues Site Visit Report 2019-09-23
- NIRB Notice to Parties re comments received 2019-08-06
- NIRB Ltr to parties requesting comment on potential project certification reconsideration 2019-08-06
- NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-07-25
- Received Project Licences, Permits and Authorizations from RAs 2019-06-10
- NIRB Ltr to Parties requesting comments on report. 2019-07-08
- NIRB Ltr to Parties requesting comments on report. 2019-07-08
- NIRB Ltr to Parties requesting comments on report. 2019-05-27
- Started project monitoring 2018-11-09
Region
- Kitikmeot
Project Images
Document Categories (click to open )
- Correspondence (7)
- Additional Project Files (26)
- General Correspondence (1)
- Comment Submissions (10)
- Screening Decision Report (4)
- Monitoring Reports (2)
- Board Voting Package (1)
- Conformity Determination (1)
- General Correspondence (154)
- Exceptions (3)
- Draft EIS (482)
- DEIS Information Requests (79)
- DEIS Technical Review Comments (33)
- Pre-Hearing Conference (124)
- Final EIS (318)
- FEIS Information Requests (1)
- Final Written Submissions (30)
- Public Hearing (218)
- Public Hearing Report (11)
- Project Certificate (7)
- Project Certificate (4)
- Authorizations (3)
- Management Plan (33)
- General Correspondence (7)
- Monitoring Report (9)
- Annual Reports (161)
- Annual Visit (3)
- Site Visit (16)
- Amendment Application (12)
- Public Hearing (2)
Project Application
Screening
Review
Monitoring
Search within selected category
All project documents;?>
Click on the icon to preview PDF. Click on the sign to view document details.
Impact Statements Submissions (click to open)
- 2018-05-04 Final IS (1 volume, 1 document)
- 2017-02-16 Draft IS (1 volume, 1 document)
- 2017-01-23 Draft IS (1 volume, 153 documents)
- 2017-01-20 Draft IS (1 volume, 74 documents)
- 2017-01-19 Draft IS (1 volume, 142 documents)
- 2017-01-18 Draft IS (1 volume, 102 documents)
- 2016-12-28 Draft IS (1 volume, 1 document)
- 2016-11-25 Draft IS (1 volume, 1 document)
- 2016-08-30 Draft IS (1 volume, 1 document)
- 2013-11-08 Draft IS (1 volume, 1 document)
- 2013-10-17 Draft IS (1 volume, 1 document)
- 2013-02-18 Draft IS (1 volume, 2 documents)
- 2013-02-11 Draft IS (1 volume, 2 documents)
- 2013-02-08 Draft IS (1 volume, 1 document)
Comment Form for NIRB Screenings
We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).
Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...
Register an Account