Project Dashboard

Status: ACTIVE MONITORING

  • NIRB File No:

    03MN107

  • Application No.:

    124588

  • Project Type:

    Mine Development

  • Project Name:

    Meadowbank Gold Project

Applicant
Primary Contact
Related Projects

The Meadowbank Gold Mine Project was assessed by the NIRB from 2003 – 2006. It was approved to proceed on December 30, 2006 subject to the terms and conditions of Project Certificate No. 004. This project dashboard contains the original assessment information as well as monitoring information through to the approval of an amended Project Certificate associated with the Amendment to Condition 32 – All-Weather Access Road in 2009.



Modified from the 2005 Project Description: The Meadowbank Gold Mine Project (the ‘Project’) involves the construction and operation of an open pit gold mine located in the Kivalliq Region of Nunavut, approximately 70 kilometres (km) north of the Hamlet of Baker Lake on Inuit-owned surface lands. The Meadowbank Gold Mine is planned to have a 12-year project life (2 years of construction, 8 years of operations, and 2 years of closure and post-closure activities), and anticipates the creation of up to 310 direct jobs through construction, and 370 jobs through operations. The Project is planned as a “fly-in/fly-out” operation with personnel rotating every several weeks. Access to the site for re-supply of materials and goods will be via a 115 km all-weather road.



The Project will include three open pits, called Portage, Vault and Goose Island to mine the estimated 2.77 million ounces of gold reserves. Water management infrastructure such as dikes and diversion channels will be utilized to dewater the pit areas following a fish-out program. Project components will include additional water management infrastructure; waste rock storage facilities, and a tailings storage area. The following on-site infrastructure is proposed to support mining activities: ore-processing plant; power plant; fuel tank farm; explosives storage area; airstrip; haul and service roads; water treatment plant; incinerators; sewage treatment facility; maintenance facility; and accommodations and camp facilities for up to 250 personnel. The Project will also include infrastructure located approximately two (2) km east of the Hamlet of Baker Lake consisting of barge unloading facilities, a storage laydown area, and fuel tank farm. Supplies will be shipped seasonally directly to the Baker Lake facility via barge.

Assessment Phase / Activity
  • Technical advisor assigned 2023-03-30
  • Technical advisor assigned 2023-02-13
  • Technical advisor assigned 2023-02-13
  • Technical advisor assigned 2023-02-13
  • Technical advisor assigned 2023-02-13
  • Technical advisor assigned 2021-10-22
  • Technical advisor assigned 2021-03-31
  • Technical advisor assigned 2021-03-31
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2020-04-23
  • NIRB Notice to Parties re Proponent response received 2020-01-31
  • Technical advisor assigned 2019-12-09
  • NIRB Issues Site Visit Report 2019-12-05
  • NIRB Notice to Parties re Proponent response received 2019-11-28
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2019-10-25
  • NIRB Issues Site Visit Report 2019-10-03
  • NIRB issues notice of community information sessions 2019-07-12
  • NIRB issues notice of community information sessions 2019-07-12
  • Additional Plans: Due Date set 2019-07-02
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-07-02
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-06-19
  • NIRB Notification to Parties Comments Received 2019-05-29
  • NIRB Ltr to Parties requesting comments on report. 2019-05-29
  • NIRB Ltr to Parties requesting comments on report. 2019-05-15
  • NIRB Ltr to Parties requesting comments on report. 2019-04-29
  • Received Project Licences, Permits and Authorizations from RAs 2019-02-19
  • NIRB Notice to Parties re Proponent Response received 2019-01-14
  • NIRB Notice to Parties re Responsible Authority Response Received 2018-12-18
  • NIRB Notice to Parties re Proponent response received 2018-12-18
  • Send Notification to Parties 2018-12-11
  • NIRB Issues Monitoring Report and Recommendations to Responsible Authorities 2018-12-03
  • Technical advisor assigned 2018-11-21
  • Technical advisor assigned 2018-11-21
  • NIRB Issues Monitoring Report and Recommendations to Responsible Authorities 2018-11-21
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-11-07
  • NIRB issues notice of community information sessions 2018-08-09
  • NIRB Ltr to Parties requesting comments on report. 2018-08-09
  • NIRB Ltr to Parties requesting comments on report. Extended 2018-06-22
  • NIRB Ltr to Parties requesting comments on report. Extended 2018-06-04
  • NIRB Ltr to Parties requesting comments on report. 2018-05-17
  • NIRB Received Report From Proponent 2018-05-10
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2018-04-30
  • Send Notification to Parties 2018-02-15
  • NIRB Ltr to Proponent re Conformity Determination required 2018-01-31
  • NIRB Notice to Parties re Proponent response received 2018-01-25
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-25
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-16
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-08-15
  • NIRB Issues notification of planned site visit 2017-08-08
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-08-08
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-26
  • NIRB Ltr to Parties requesting comments on report. 2017-06-26
  • NIRB Ltr to Parties requesting comments on report. 2017-05-25
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-06
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-04
  • NIRB Notice to Parties re Proponent Response received 2016-12-15
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2016-11-04
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2016-11-04
  • NIRB Issues Amended Project Certificate to Proponent 2016-08-12
  • NIRB Issues Amended Project Certificate to Proponent 2016-08-12
  • NIRB Notice to Parties re Project Certificate Workshop 2016-08-11
  • NIRB Notice to Parties re Project Certificate Workshop 2016-08-10
  • Received Project Licences, Permits and Authorizations from AAs 2016-08-02
  • NIRB Site Visit: Notice of Visit to RIA sent 2016-08-02
  • NIRB Notice to Parties re Project Certificate Workshop 2016-07-29
  • NIRB Received Minister’s decision re Final Hearing Report 2016-07-28
  • NIRB Received Report From Proponent 2016-04-28
  • NIRB Ltr to Minister(s) re Final Hearing Report 2016-04-20
  • NIRB Notice to Parties re Final Hearing Transcripts 2016-04-20
  • Notice to Parties re Comments on Draft Hearing Agenda 2016-04-20
  • Technical advisor assigned 2016-01-29
  • Started project monitoring 2005-09-14
Region
  • Kivalliq
Project Images
/
Document Categories (click to open )
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account