Project Dashboard
Status: COMPLETED SCREENING
-
NIRB File No:
17EA068
-
Application No.:
125187
-
Project Type:
Mineral Exploration
-
Project Name:
Huckleberry Claim
Completed Screening
- Screening Decision Issued 2018-03-23
- File Closed 2018-03-23
Applicant
- John Tugak
- PO Box 14
- Arviat, Nunavut X0C-0E0 Canada
- jtugak@hotmail.com
Primary Contact
- Agnico-Eagle Ltd., David Frenette
- Agnico-Eagle Ltd., David Frenette
- P.O. Box 87, chemin de la mine Goldex
- Val-d'Or, Qc J0Y1Z0 Canada
- Tel: 819-874-5980
- david.frenette@agnicoeagle.com
Regulatory Authorities
External Links
Project Summary
John Tugak signed a mineral exploration agreement with Nunavut Tunngavik Incorporated to obtain the rights on some mineral properties located mostly west of the Whale Cove community and North and Northwest of the Arviat Community.John Tugak signed on June 30, 2017 an agreement with Agnico Eagle Mines Limited (Agnico Eagle) to continue exploration activities on one of his properties, the property Huckleberry-0001. This property is located on Inuit Owned Land surface and subsurface, approximately 65 km mostly west of the Whale Cove community. Exploration activities, such as prospecting, have already been authorized by Nunavut Planning Commission (NPC), Nunavut Impact Review Board (NIRB) and Kivalliq Inuit Association (KIA). The present application is to permit the installation of an exploration camp on the Huckleberry-0001 property, to permit additional exploration activities including geophysical surveys (airborne and ground support), diamond drilling, rab drilling, trenching and to permit the use of a winter access from the Meliadine area and from Whale Cove up to the Huckleberry-0001 property. Agnico Eagle will manage the exploration activities on this property and will be responsible for its activities.The exploration camp is planned to be installed at the same location where the former exploration camp was installed in the area of the closed portal.
Assessment Phase / Activity
- Application screening completed 2020-08-27
- Technical advisor assigned 2020-04-16
- Technical advisor assigned 2020-04-16
- Application screening completed 2020-01-09
- Received Project Licences, Permits and Authorizations from AA 2018-10-25
- Minister Response Received 2018-09-05
- Minister Response Received 2018-04-23
- Application screening completed 2018-03-23
- NOI Issued 2018-03-23
- SDR Issued 2018-03-23
- Board voting 2018-03-22
- Extention to Screening Deadline requested 2018-02-16
- Opportunity to Respond 2018-03-02
- Opportunity to Respond Extended 2018-02-15
- Opportunity to Respond Extended 2018-02-13
- Opportunity to Respond Extended 2018-01-30
- Opportunity to Respond in progress 2018-01-29
- Received Comment submissions from Parties: Notice re comments received 2018-01-15
- Extention to Screening Deadline requested 2017-12-13
- Commenting period 2018-01-12
- Application screening started 2017-12-13
Region
- Kivalliq
Project Images
Document Categories (click to open )
Search within selected category
All project documents;?>

Click on the


Comment Form for NIRB Screenings
We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).
Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...
Register an Account