Project Dashboard

Status: COMPLETED SCREENING

  • NIRB File No:

    17EA068

  • Application No.:

    125349

  • Project Type:

    Mineral Exploration

  • Project Name:

    Whale Cove Area, Exploration Projects

Completed Screening

Applicant
  • Agnico Eagle Mines Ltd., David Frenette
  • Agnico-Eagle Ltd., David Frenette
  • P.O. Box 87, chemin de la mine Goldex
  • Val-d'Or, Qc J0Y1Z0 Canada
  • david.frenette@agnicoeagle.com
Primary Contact
External Links

Non technical summary Whale Cove Area, Exploration ProjectsAgnico Eagle Mines Limited (Agnico Eagle) possesses mineral properties located on Crown and Inuit Owned Land in the area located between 20km to 70km of the Whale Cove community. The exploration activities planned on these properties include drilling, prospection and geophysical surveys. Winter accesses from the Meliadine Mine site and from the Whale Cove community up to some of the exploration areas were screened by NIRB in decision 17EA068. This decision concerned the Huckleberry exploration project. The present application has been prepared to obtain the authorizations for exploration activities in additional areas and also include the installation of an exploration camp in one of these areas. The winter accesses already screened will allow Agnico Eagle to transport material and equipment from the Meliadine Mine and from the Whale Cove community to the exploration sites during the winter, thus reducing the use of helicopters during the exploration season. At this time, a limited quantity of material and equipment is planned to be transported, since these exploration projects are at an initial stage. Winter accesses will be used by tracked tractors (Challenger), passing directly on the ice and snow ensuring soil protection. Snowmobiles could also use these accesses.

Assessment Phase / Activity
  • Received Annual Report from Proponent 2024-01-31
  • Received Annual Report from Proponent 2023-05-04
  • Received Annual Report from Proponent 2022-12-13
  • Received Annual Report from Proponent 2022-03-31
  • Received Annual Report from Proponent 2021-07-20
  • Technical advisor assigned 2021-07-19
  • Received Annual Report from Proponent 2020-07-08
  • Technical advisor assigned 2020-06-17
  • Exempt from Screening 2018-08-31
  • Application screening completed 2018-07-31
  • NOI Issued 2018-07-31
  • SDR Issued 2018-07-31
  • Board voting 2018-07-26
  • Extention to Screening Deadline requested 2018-07-13
  • Opportunity to Respond 2018-07-18
  • Opportunity to Respond 2018-07-12
  • Received Comment submissions from Parties: Notice re comments received 2018-07-04
  • Commenting period 2018-07-03
  • Application screening started 2018-06-06
Region
  • Kivalliq
Project Images
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account