Project Dashboard

Status: ACTIVE MONITORING

  • NIRB File No:

    08MN053

  • Application No.:

    125710

  • Project Type:

    Mine Development

  • Project Name:

    Production Increase Proposal Renewal

Applicant
Primary Contact

The Production Increase Extension Proposal associated with the approved Mary River Iron Mine was assessed by the NIRB in 2019-2020. It was approved to proceed on June 18, 2020 subject to the terms and conditions of Project Certificate No. 005 Amendment 3. Baffinland Iron Mines Corporation (Baffinland) is a Canadian mining company operating the Mary River Mine Project (the Project). The Project is an open pit iron ore mine located in the Qikiqtani Region of Nunavut on northern Baffin Island, approximately 160 km south-southwest of the nearest community of Pond Inlet (Mittimatalik) and 1,000 km north-northwest of the territorial capital of Iqaluit. Baffinland received regulatory approval for the Project in 2012. The Approved Project authorizes Baffinland to mine up to 18 Million tonnes per year (mtpa) from Deposit No. 1. In 2014, Baffinland received approval for an amendment to the Project, called the Early Revenue Phase (ERP), which allows for the additional extraction, transport and shipment of 4.2 Mtpa along a tote road to Milne Port where the iron ore is then shipped to international markets. The Production Increase Proposal Renewal is requesting approval to continue to produce and transport up to 6 mtpa via truck along the Tote Road and 6 mtpa via ore carrier along the established shipping season (July to October) and route through the Northern Transportation Corridor to the end of 2022. Purpose and Need. Baffinland has demonstrated operational improvements and efficiencies since the Project became operational in 2015. Sustaining activity levels at the same 6 mtpa rate that applied between 2018 and 2021 will avoid the need to scale back operations, which would significantly impact the important employment and contracting opportunities provided by the Project, as well as the benefits that flow to Qikiqtani Inuit (managed on behalf of Qikiqtani Inuit by the Qikiqtani Inuit Association). The current amendment is an interim measure to maintain the status quo while Baffinland explores alternative long-term solutions to the challenges presented by operating a high-cost Arctic Project while being subject to highly variable global iron ore market prices. Project economics have continued to be a key driver in the development of the Mary River Project and reducing the production and transportation of iron ore to 4.2 Mtpa will guarantee seasonal closures and threaten the long term viability of the mine. The company has currently positioned itself during the first seven years of operation to increase the efficiency of the trucking operation and allow for the advancement of production limits under current operations.

Assessment Phase / Activity
  • NIRB Issues Site Visit Report 2023-10-27
  • Send Notification to Parties 2023-10-03
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2023-08-14
  • NIRB Notice to Parties re Proponent Response received 2023-08-14
  • Send Notification to Parties 2023-08-04
  • Send Notification to Parties 2023-08-04
  • Send Notification to Parties 2023-07-31
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2023-07-13
  • Send Notification to Parties 2023-07-06
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2023-06-29
  • Send Notification to Parties 2023-06-14
  • NIRB Issues Site Visit Report 2023-06-13
  • Send Notification to Parties 2023-06-06
  • Send Notification to Parties 2023-05-31
  • NIRB Ltr to Parties requesting comments on report. 2023-05-31
  • Send Notification to Parties 2023-05-24
  • Send Notification to Parties 2023-05-17
  • Send Notification to Parties 2023-05-17
  • Send Notification to Parties 2023-05-17
  • Send Notification to Parties 2023-05-09
  • Send Notification to Parties 2023-05-08
  • Send Notification to Parties 2023-05-04
  • Send Notification to Parties 2023-05-04
  • Send Notification to Parties 2023-04-21
  • Send Notification to Parties 2023-04-19
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2023-03-16
  • NIRB Final Monitoring Report: Sent to Distribution 2023-02-17
  • Send Notification to Parties 2023-02-16
  • Send Notification to Parties 2023-01-06
  • Send Notification to Parties 2022-12-14
  • NIRB Final Monitoring Report: Sent to Distribution 2022-12-06
  • NIRB Issues Amended Project Certificate to Proponent 2022-11-07
  • NIRB Issues Amended Project Certificate to Proponent 2022-11-03
  • NIRB Issues Amended Project Certificate to Proponent 2022-11-03
  • Send Notification to Parties 2022-10-26
  • NIRB Issues Correspondence to Parties re Project Certificate Terms and Conditions 2022-10-19
  • NIRB Notice to Parties re Project Certificate Workshop 2022-10-19
  • NIRB Notice to Parties re Project Certificate Workshop 2022-10-12
  • NIRB Notice to Parties re Project Certificate Workshop 2022-10-12
  • NIRB Received Minister’s decision re Final Hearing Report 2022-10-12
  • NIRB Ltr to Minister(s) re Final Hearing Report 2022-09-22
  • Send Notification to Parties 2022-08-26
  • Send Notification to Parties 2022-08-25
  • Send Notification to Parties 2022-08-23
  • Send Notification to Parties 2022-08-23
  • Send Notification to Parties 2022-08-19
  • Send Notification to Parties 2022-08-18
  • Send Notification to Parties 2022-08-15
  • Send Notification to Parties 2022-08-15
  • Send Notification to Parties 2022-08-12
  • Send Notification to Parties 2022-08-12
  • Send Notification to Parties 2022-08-12
  • Send Notification to Parties 2022-08-10
  • Send Notification to Parties 2022-08-10
  • Send Notification to Parties 2022-08-04
  • Send Notification to Parties 2022-08-03
  • Send Notification to Parties 2022-08-02
  • NIRB Ltr to Parties re Community Representatives for Community Roundtable at Public Hearing 2022-07-29
  • Send Notification to Parties 2022-07-27
  • Send Notification to Parties 2022-07-26
  • Send Notification to Parties 2022-07-25
  • NIRB Ltr to Proponent re reconsideration of Project Certificate 2022-07-19
  • Send Notification to Parties 2022-07-14
  • Send Notification to Parties 2022-07-12
  • Send Notification to Parties 2022-07-06
  • Send Notification to Parties 2022-07-06
  • Technical advisor assigned 2022-07-06
  • Send Notification to Parties 2022-06-24
  • Send Notification to Parties 2022-06-17
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2022-06-28
  • Started project monitoring 2022-06-13
Region
  • North Baffin
Project Images
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account