Project Dashboard
Status: COMPLETED SCREENING
-
NIRB File No:
23YN040
-
Application No.:
125845
-
Project Type:
Scientific Research
-
Project Name:
Long Term Water Project - Geotechnical Investigations
Completed Screening
- Screening Decision Issued 2023-06-23
- File Closed 2023-11-02
Applicant
- City of Iqaluit
- Tamilore Adeleke
- Po Box 460 (1085 Mivvik Street)
- Iqaluit, Nunavut X0A0H0 Canada
- t.adeleke@iqaluit.ca
Primary Contact
- City of Iqaluit
- Tamilore Adeleke
- Po Box 460 (1085 Mivvik Street)
- Iqaluit, Nunavut X0A0H0 Canada
- Tel: 8672222950
- t.adeleke@iqaluit.ca
Regulatory Authorities
External Links
Project Summary
The City of Iqaluit is facing critical challenges with its drinking water supply due to its growing population and the impact of adverse climate changes. To address this pressing issue, the City and their consultants will progress designs for upgrades to its water supply and distribution infrastructure systems. The upgrades are anticipated to include pumping and conveying water from Qikiqtalik Lake (also known as Unnamed Lake) through conveyance pipes to a newly constructed earth berm storage reservoir located adjacent to Lake Geraldine. The source water upgrades will primarily comprise three key aspects: raw water extraction, raw water conveyance, and raw water storage. To advance the engineering design of these upgrades, and ahead of future permitting phases, it is imperative that thorough geotechnical field investigations are completed. These investigations aim to assess existing site features and underground conditions. For timeframe of these investigations, the City anticipate to commence geotechnical field investigations in 2023, with completion anticipated during the summer of 2024. The purpose of this project is to advance the project geotechnical investigations. The geotechnical investigation will study the surface and subsurface conditions of the future pump station, the conveyance pipe, and the reservoir to determine if the sites are adequate to proceed with design, permitting and construction activities. A research geotechnical drilling program will be implemented to coordinate the field investigation and will consist of an estimated total of 24 boreholes (12 boreholes at ~5m depth and 12 boreholes at ~10m depth). For the raw water conveyance pipe, there are two potential alignment options identified in prior studies. Both alignments are roughly the same distance and therefore will require approximately 12 boreholes in total for a geotechnical study. Six (6) of those boreholes at 5-meter depth and six (6) of those at 10-meter depth along the line. Some of those mentioned 12 boreholes will also include the pump station structure for the geotechnical study. The new reservoir will require the other 12 boreholes, six (6) at 5m depths and six (6) at 10m depths. The exact locations will be based on project consultants’ recommendations and on-site conditions/surveys. However, the tentative Geotechnical investigation boreholes would be located in three approximate areas:1. At the proposed pump station site adjacent to Unnamed Lake on the south side in an investigation area approximately 10 m x 10 m and centered at Latitude 63.779769, Longitude -68.4504122. At the proposed reservoir site adjacent to Lake Geraldine on the East side in an investigation area approximately 750m x 350m and centered at Latitude 63.761552& Longitude -68.492085 3. Along the proposed conveyance pipe routes (2) which extend approximately 5 km between the pump station and reservoir with each route comprising an investigation width of 10mThe project proponent will prepare essential management plans, including a spill contingency plan, health and safety plan, refueling procedures, and erosion and sediment control plan for reinstating any impacts resulting from localized boreholes upon the completion of the research activity. Particular attention will be given to avoiding disruption to areas housing fragile vegetation or wildlife. The use of non-toxic drilling fluids will be used to prevent any contamination of water bodies in the vicinity.
Assessment Phase / Activity
- Application screening completed 2023-11-02
- NOI Issued 2023-11-02
- SDR Issued 2023-11-02
- Board voting 2023-10-30
- Board voting 2023-10-25
- Technical advisor assigned 2023-10-04
- Received Comment submissions from Parties: Notice re comments received 2023-09-20
- Extention to Screening Deadline requested 2023-08-30
- Commenting period 2023-09-20
- Application screening started 2023-08-28
Region
- South Baffin
Project Images
Document Categories (click to open )
Search within selected category
All project documents;?>

Click on the


Comment Form for NIRB Screenings
We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).
Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...
Register an Account