Status: COMPLETED SCREENING

  • NIRB File No:

    20YN021

  • Application No.:

    125552

  • Project Type:

    Scientific Research

  • Project Name:

    Tallurutiup Imanga Underwater Noise Baseline Pilot

Completed Screening

Applicant
Primary Contact
Regulatory Authorities

Parks Canada Agency, Tallurutiup Imanga National Marine Conservation Area (TINMCA), is proposing a three year pilot project to gather underwater noise baseline data in the area of Arctic Bay, running through open water seasons in 2020, 2021, and 2022Lead of the Project is Clare Kines, Inuit Stewardship Co-ordinator for TINMCA. This proposal is designed to begin establishing baseline data on underwater noise, within TINMCA. TINMCA is currently in the establishment phase but has been operating since the signing of an Inuit Impact Benefit Agreement in August 2019. The pilot project will involve deploying four hydrophones in strategic spots within TINMCA in the area of Arctic Bay. This work would contribute to better understanding human generated noise and its effects on marine life and ocean health within the NMCA. This pilot underwater noise study is consistent with similar studies done in the Arctic and in Canada. It is expected that the result of this study would contribute to the overall understanding of human generated noise on marine wildlife. Once the data is analyzed, the results will be shared with the Hunter and Trapper Organization of Arctic Bay, the Hamlet, and the community at large. The following are the proposed locations:1) Adam’s Sound, the approach to the community of Arctic Bay;2) Strathcona Sound, the approach to the Nanisivik Naval Facility; 3) near Kakiak Point on Admiralty Inlet, an important area for the harvest of Narwhal by Arctic Bay Community members, and an important area of Narwhal habitat; and4) the area in the vicinity of Sannirugaaluit (Yeoman Island), an area that should have less anthropogenic underwater noise. The exact locations will be confirmed after further consultation with the community, including Arctic Bay Hunter and Trapper Organization, the Hamlet, and QIA. Discussion with QIA is also ongoing to explore potential partnership between Parks Canada and the Inuit Stewards regarding the deployment and recovery of the hydrophones. 2020 is an important year to start baseline data, as Covid-19 has reduced the amount of ship traffic that should be present in the Arctic. The four hydrophones that are to be deployed are Micro Aural hydrophones (Multi-Electronique Ltd.), locations 1-4 on the map. These hydrophones will be deployed annually over three years during the open water season. They would be deployed in waters less than 30 metres deep, using an anchor and surface buoy (see below photos of the hydrophones and quick release devices). At the earliest, initial deployment would take place in mid-August and the sites revisited in 5 week intervals (in late September and early November). An alternative mooring may be used, consisting of a subsurface buoy, and a Vemco Ascent acoustical release, depending on circumstance. In the case of the subsurface mooring, an anchor made of local rock with an eye bolt would be left behind. The acoustic devices also obtain data on tagged Greenland sharks as part of an ongoing study by Nigel Hussey of the University of Windsor. He has been using similar devices throughout Baffin Bay, including around Pond Inlet, Clyde River and Qikiqtarjuaq, to monitor the movement of 180 Greenland sharks in order to support sustainable fisheries management and development of community fisheries. Nigel Hussey’s research is conducted through the support of local HTOs, the Government of Nunavut and the Nunavut Fisheries Association with relevant licenses to fish obtained through the Department of Fisheries and Ocean. Basically, Nigel Hussey will lend Parks Canada some of his Vemco Ascent acoustical release to make the underwater noise baseline pilot project more efficient, while collecting data on Greenland sharks for him. Hydrophones record sound, they do not make sound. They are passive and remain in one spot. Further, surface floats to which the hydrophones are attached are small vinyl floats that will not cause damage to boats and create no risk to wildlife. This technology, although relatively new, is in place throughout the Arctic and the rest of Canada and has been used by government and universities. During the 2nd visit the data would be downloaded and the battery recharged. The equipment will be removed from the site during the 3rd visit in late October / early November. Dates may be adjusted to account for ice and other local conditions. The hydrophones are set to sample at 96,000 Hz and record at 15 minutes out of each hour, for approximately five weeks each deployment. It is important to note that the hydrophones record sounds only, and do not make any sound. No camp is planned, visits will be by boat. Vessels utilized to deploy and recover the hydrophones would be welded aluminum runabouts, not exceeding 28 feet, and powered by outboard motors. It is anticipated that either Arctic Bay Adventures’ boat, or one used by the Inuit Stewards would be used, but circumstances may dictate similar boats being used. Social distancing and other Covid-19 protective measures will be followed as recommended by the Nunavut Health Authority and the Arctic Bay community council (e.g. use of personal protective equipment). Data obtained would be recordings of underwater noise, including marine mammals, benthic organisms (animals that live on the bottom of the ocean), ship traffic, small vessel traffic, and ice. Data will be used to establish the baseline of underwater noise within TINMCA, in proximity of Arctic Bay. It is expected that the baseline data could help better understand the impact of underwater noise on, marine mammals within TINMCA, and could be used to complement the work on similar initiatives conducted in Nunavut waters and elsewhere.

Assessment Phase / Activity
  • Received Project Licences, Permits and Authorizations from AA 2021-06-14
  • Application screening completed 2020-10-13
  • NOI Issued 2020-10-13
  • SDR Issued 2020-10-13
  • Board voting 2020-10-06
  • Board voting Extended 2020-10-05
  • Board voting 2020-10-02
  • Extention to Screening Deadline requested 2020-09-23
  • Received Comment submissions from Parties: Notice re comments received 2020-09-16
  • Commenting period 2020-09-16
  • Commenting in progress 2020-09-08
  • Application screening started 2020-08-13
Region
  • North Baffin
Project Images
Click on document name to download it, or select the document to add to a download list.
Click on the icon to preview PDF.  Click on the sign to view document details.
Documents within selected category
Display per page:
Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account